North Olympic Salmon Coalition staff were onsite at 3 Crabs observing flood conditions during the recent heavy rain events, and passing information on to project engineers.  Check out the photos!

Looking southeast up meadowbrook creek from the bridge

Looking south from bridge
 

Bridge conditions 11:34 a.m. December 11th, 2014.
Approximately .5 inches of clearance under bridge joist.


As we enter 2015, engineers are continuing their design work on the 3 Crabs Restoration Project, and Salmon Coalition staff have begun writing project permit applications. 

Engineers need additional  information about soils in the location of the new road bed in order to satisfy county requirements for road design. There will be equipment on the Dungeness Habitat property in early February to complete this work. 

Construction dates have been shifted to Summer 2016, provided the remaining engineering and permitting goes smoothly.